ON THE AGENDA | Capital works program, Operations, and more

DOUGLAS SHIRE COUNCIL

STAFF WRITERS

Email
Last updated:


The overall delivery of the 2019/2020 capital works program has progressed as planned with eight per cent of the budget spent ($1.27 million) and a further 16 per cent committed ($2.55 million) to 30 September 2019.

A total of 24 per cent is either completed or under contract.

This will be presented at Council’s ordinary meeting on Tuesday at Council Chambers in Mossman.

Other items on the agenda are the monthly financial report for September 2019; the operational plan progress report for July to September 2019 and the CEO’s report for July to September 2019.


Douglas Shire Council
Ordinary meeting
Tuesday, 22 October 2019, 10:00am

Table of contents

1. Capital works progress report for the 1st quarter 2019 – 2020
2. Monthly financial report for September 2019
3. Operational plan progress report for July to September 2019
4. CEO report for July to September 2019 

 